Project:Dexus Richlands Warehouse Stage 1
Builder: McNab Developments (Qld) Pty Ltd
Developer: Dexus
Overview:
Industrial facility with over 50,000m2 of warehouse floor area, office space and external hardstand. Final result - FF 80 / FL 78. Kraftur® crew member Travis was also awarded with the safety award.
Scope of works:
- Install polythene membrane to underside of slabs.
- Formwork to Loading Dock Leveller set down including casting-in angles/box.
- Edge form to ground slabs.
- Formwork to column block outs.
- Supply and install Armour Joints to FRC slabs.
- Install isolation joints to panel and block outs.
- Fix mesh and bar reinforcement.
- Place and finish Loading Dock slabs.
- Place and finish Internal Warehouse FRC slabs.
- Supply and apply CR curing compound.