Project: Gold Coast Airport RPT Apron Upgrade Stage 2B
Builder: SEE Civil
Address: Gold Coast Airport, Bilinga

Overview:

The Gold Coast Airport RPT Apron Upgrade Stage 2B works are a continuation of the Gold Coast aircraft pavement Stage 2 and Stage 2A upgrade works, which were also completed by Kraftur®. The project, like the previous stages, had highly demanding aircraft pavement specification requirements to be met – which Kraftur® again achieved again through close consultation and engagement with the client and the concrete supplier on the project.

Scope of works:

  • Supply and installation of custom engineered timber aircraft pavement formwork that conforms to precise specification tolerances for the formwork’s alignment, level, movement limits and dowel positioning.
  • Installation of a reinforcing bar.
  • Place, compact and finish aircraft pavement concrete according to project specification, using a vibrating truss screed and bridge while monitoring and maintaining optimal environmental conditions for concrete as specified.
  • Continuous wet curing of concrete for seven days using hessian mats and soaker hoses
  • Saw cutting, joint widening and joint sealing of apron pavement as specified.