Project: ARROW Transport Industrial Development

Builder: McNab Qld Pty Ltd.

Address: 8 Bishop Drive, POB QLD

 

Overview

Kraftur® securing and completing one of the major industrial development for Port of Brisbane working with McNab i.e., ArrowTransport from footings to crossovers. Kraftur® successfully delivered place and finish solutions from footings to crossovers for circa >26,000m2 of 300mm thick post tensioned heavy duty container pavements and 8,000m2 of warehouse with offices.

Key Highlights

  • Placed concrete to retaining wall footings and workshop area
  • 8,000 m2 of internally laid burnished concrete slabs for facility, amenities area and main offices
  • Placed concrete to workshop area
  • Screeding high fibre mix to post-tensioned 330mm thick heavy-duty pavements to >26,000 m2 of estate in early morning starting works from 2:30am.
  • Laid another 7,000m2 of stack pavements, footpaths, sprinkle tanks and light duty pavements
  • Completed the job by pouring 4 crossovers and sign footings.

 

Kraftur® Project Team:

  • Operations Manager – David Lowry
  • Site Manager – John Nolan
  • Contracts Manager – Aagu Shah
  • Safety Manager – Michael Rawlinson
  • Project Director – Adrian Prevost

 

Challenges and Solutions

Challenge: Programming challenges to principal contractor due to weather conditions.

Solution:

  • Kraftur® manage to offer consultation on PT designs, manage early morning pours with crew and delivered successful placing to all heavy-duty hardstands in checker style solution.
  • Kraftur® offered solution to change EDJ6 (Lesa type G joint) to Lesa Type B joint with full separation plate for enabling crew to pour over and still support engineering requirements.
  • Kraftur® offered solution of using Piekko EXA joint to reduce number of pours for 230 stack container
    area and accelerate the principal contractor’s programme.