Project: ARCO Industrial Facility
Builder: Multispan Australia
Address: 15 proximity place, Stapylton, QLD
Overview
Kraftur® completing first project for Multispan Australia. Partnering with Boral for a supply, place and finish solution from bored piers to crossovers, Kraftur® crew has brought to life this ARCO industrial development of 5,000m2 internal and 8,000m2 external hardstands at Stapylton, QLD.
Key Highlights
- Supply, drilled and placed concrete to more than >30no x 6m deep bored piers on hard rock conditions
- 5,000 m2 of internally laid conventional concrete slabs to falls for facility
- Clearing subgrade, supply, place and finish 8.000m2 concrete heavy-duty hardstand, coupled with asphalt driveways, and car-parks.
- Supply, place and finished concrete to 1 no x Main office ground slab and suspended slab with 8 ins-situ columns
- 1x no. sprinkler tank, 1 x no. Pump room building, 1 x smoker’s hut and 1 x no. Dock office.
- 1.5m wide footpaths, pathways and 2xno crossovers
Kraftur® Project Team:
- Operations Manager – David Lowry
- Site Manager – Jarad Glover
- Contracts Manager – Aagu Shah
- Defects & technical Remedial Manager – Richard Booth
- Project Director – Paul Ryan
Challenges and Solutions
Challenge:
- Working in flat floor competitive market, Kraftur® had to crack the code with Multispan Gold-coast team and win first tender at right price with our preferred subcontractor.
- The civil contractor could not keep up with preparing the subgrade for Kraftur® to start preparation on external hardstands.
Solution:
- Kraftur®’s contract management team went on sharp pricing on basis of support provided by our partners Boral and Mesh & bar. Kraftur® offered a coffee machine to MSA Gold coast office to fuel the bustling and start of a strong partnership.
- Kraftur® offered to support MSA team on taking that scope under day works and prepared the estate for our steel fixers to start installing mesh and keep up with the programme.